A Case Study – Vendome Mall Project for the MEP Construction Management
![]() |
| Photo-1: Designed Snowpark and Family Entertainment Center (courtesy-CRC/MSAZI) |
“This article is an excerpt topic in the Thesis Dissertation
from PUP (Polytechnic University of the Philippines) Master of Science in
Construction Management (MSCM), and theoretical research background of Ph.D.
Courses in Building and Construction Engineering (AIU SSE USA) about the case study of Vendome Mall
Project for the MEP Construction Management, relevance to job safety in the
prevention of accident and injuries based on the critical phases, and functions
within the construction environment involving various facilities.”
Insight
The Vendome Mall - Snowpark and Family Entertainment Center
is currently in progress. The contracted work discussed herein deals with the
supply and installation of MEP Services (HVAC, Firefighting, Water Supply,
Drainage, and Electrical Systems). The designed intent is to create an
entertainment facility to be rated as one of the most fascinating and majestic
structures (Photo-1). The Snowpark and Family Entertainment Center soar to a
height of 17-meters inside the building as shown in Photo-3. The Vendome Mall
building stands (Photo-2) on an artificial island in the Lusail area near to
the West Bay Doha, which can be reached in just 15-minutes’ drive from City
Center of Doha. The Main Contractor was awarded the MEP contract to provide a
unique services engineering solution that would match the unique construction
requirement and challenges for the Snowpark, Family Entertainment Center, and
the entire project safety requirements.
Case
Study Solution in the Improvement of the Current Project
During
the construction process, working hand in hand with the Project Main Contractor
and the Project Consultant the MEP Sub-Contractor suggested improvements in the
design drawings for securing better safety and a healthy environment.
![]() |
| Photo-2: Vendome Mall Aerial View (courtesy- CRC) |
Amongst the myriad challenges that occur in the construction
industry, an MEP Sub-Contractor faces multiple issues during the ongoing
installation/ construction. Hence, careful consideration was given to the
designs, to satisfy the requirement in a safe manner, of all engineering
works before starting site construction.
Since
the MEP Sub-Contractor is at the forefront for all the systems works they have
initiated the safety policy and review for providing solutions to achieve the
target.![]() |
| Photo-3, Snowpark & Family Entertainment Center Construction in progress (photo by rvgomeseria) |
Responsibilities
For effective control, the construction responsibilities have
been allocated for the improvement of the organization of the construction
activities. They comprise the followings:
- The Main Contractor awarded the contract to the MEP Sub-Contractor who is responsible for the overall implementation of the work procedures as specified.
- The Construction MEP Project Manager along with his Discipline Engineers, Site Supervisors, Surveyors, and Foreman is to ensure that all the works are carried out according to the approved Specifications, Drawings, and Method Statements.
- The Quality Assurance and Quality Control (QA/QC) Manager along with the QC Engineer ensures that all the works are carried out as per Specification; Issued for Construction (IFC) Drawings, Method Statement and Inspection Test Plan (ITP). The Quality Assurance and Quality Control (QA/QC) Manager must coordinate with the site for off-site tests related to the Contracted Works.
- The Health, Safety, and Environment (HSE) Manager along with the Safety Officer is to ensure the implementation of all Safety Procedures and Safety Measures related to the nature of works being carried out within the construction environment and in accordance with the Health, Safety, and Environment (HSE) plan.
The full workforce is deployed on-site all the requisite
materials and equipment are ordered and engineering works submission and
approvals are quickly resolved on all issues in the design via shop drawings
submission and approvals to meet the project timeframe and thereafter executing
the work promptly. Thus, the resulting efforts by the team produce work with
reliability and accuracy, in fact, improve on them since it is wastage has
also been minimized.
Safety
Hazards and Preventive Measures in the Construction
The hazards associated with the installation of MEP/ Building
Services and all related work activities are controlled as per the required
risk assessment of such; 1) PPE Requirements, and 2) Information and
Communication with the Personnel.
PPE
Requirements
As
a minimum requirement as discussed above, the following PPE has been used by
the Staff and Labour employed on the construction site as such: 1) Safety Helmet, 2) Safety shoes, 3) Coverall, 4) Hand
gloves, 5) Full body harness, 6) Earplugs, 7) Eye protection/ goggles, and 8) Special
respiratory mask/ dust mask.
Information
and Communication to the Personnel
- Safety induction has is done in accordance with the HSE Policy prior to the start of the work on the construction site.
- Job Stat Card is known as the 4C (Control, Cooperation, Communication, Competence) and the Safety Tool Box is carried out prior to starting work.
- The Method Statement and the Risk Assessment briefing are convened and attended by all personnel assigned to do the task within the construction environment and all risks associated with the works are explained.
- The Safety Personnel and the designated Responsible Person ensure that all works on site are carried out and all statutory requirements are complied with before any works commence.
- Since the work is in the construction area, all measures are in place for minimizing/ eliminating dust exposure.
- An emergency evacuation plan is explained to all workmen to deal with emergency situations on the construction site.
- Periodically a Hazard Analysis is done for safety.
- All personnel is trained with the correct equipment set up on site.
The Case Study Benefits
The Vendome Mall - Snowpark and Family Entertainment Center
is one of the most important landmarks in Qatar. Considering the harsh climate
conditions and the construction standards set up for achieving high-quality MEP
/ Building Services for the facility not only to meet the client’s expectations
but to try to exceed them.
In the ongoing construction, the principle is meeting the
strength requirements they have provided by securing a total designed solution
environmentally which will result in expanding life expectancy for the building
structure, design safety, and energy conservation.
Conclusion
At a Construction Site, the Construction Project Manager is
responsible for the Safety and Health of the employees on behalf of the Owner
while still having to complete the project as per the approved design plans, the
scope of works and specifications. The Project Manager faces challenges from
the grass-roots level since he is responsible for the overall success of
delivering the owner’s physical development within the constraints of a project
cost, time, quality, environmental and safety requirements
With the increase in complexity of projects and consequently
of the construction processes ensuring awareness of Safety, Health, and Security
are extremely important. The processes and practices must have adhered to in spite
of increasing nuisance from non-stakeholders since Owners demand accountability
and proper guidance during the entire planning and construction process, all as
approved by an authority.
The Project Manager must be technically competent and be able
to adapt to the changing requirements of the built environment by relying on
the knowledge and skills acquired through training, education, and hands-on
experiences. The Project Manager needs to also have skills to meet play the
roles and bear the responsibilities to create wisdom, distribute the wisdom,
and identify hindrances to knowledge acquisition.
PMI defining project management as "the application of
knowledge, skills, tools, and techniques to a broad range of activities in
order to meet the requirements of a particular project." HSE
covers all phases of a project. In today's competitive environment, the
construction technological aspects need to be designed for timely information
to enable the preparation of engineering works, procure the required materials
from the market and deploy the necessary labor, plant, and equipment so that
productivity remains high. The processes discussed earlier provide an essential
compendium in the construction industry for securing safety for all practicing
engineers, designers, planners and other practitioners since Safety, Security
and Health encompasses all the phases of planning, design, and construction from
start to finish.
Write-Up References can be Read from this
Links;
Gomeseria, RV; (September
2019); “Planning, Design
& Construction - Safety & Security Policy;"
CEAI ViewPoint Journal; September 2019 Edition; Consulting Engineers Association
of India
Gomeseria, RV; (September 2019); “A Case Study -Vendome Mall Project for the MEP
Construction Management;” Retrieved from; https://www.researchgate.net/publication/335751525_A_Case_Study_-Vendome_Mall_Project_for_the_MEP_Construction_Management


To cite this blog / article paper; Gomeseria, R. V. (2019, September 11). A Case Study – Vendome Mall Project for the MEP Construction Management. https://doi.org/10.17605/OSF.IO/RN85E